The Yorkshire Compute Belt

Sites / Deep Green Bradford

Deep Green Bradford

Deep Green · proposed · City of Bradford Metropolitan District Council

5.6 megawatt heat-reusing facility at Listerhills / Thornton Road. News reports say Bradford Council approved it in May 2026. We still list it as proposed until we can link the live council planning page.

Stated size

6 MW

biggest size stated for this site Operator

Source: Deep Green press materials / BBC reporting

The largest megawatt figure on the public record for this one site (planning docs or operator materials). It may include stages that are not built yet. Not everyday electricity use; the source sits with the number. Stated size is not electricity use.

Site area

1 acres

active industrial Operator

What was here: Land east of Bradford Energy Centre (temporary contractor/storage area under energy-centre consent)

Water

Zero

litres/year · operator claim Operator

Deep Green claims cooling eliminates water use. That is their claim, not a metered reading.

Equivalences

No operator on this map discloses expected load factor (the share of peak power used on average), so yearly electricity figures are shown as a range, not as a known total.

Cooling

Closed-loop cooling; up to 95% of heat reused into Bradford Energy Network; zero water use claimed Operator

Claims on record

Disclosure checklist

Plain checklist, no aggregate score.

Right of reply

Right of reply: open; no response received. Email marco@prismaticlabs.ai. Subject is prefilled. Or see methodology.

Timeline

  1. 2025-07: Deep Green files for Bradford heat-reuse data centre beside Bradford Energy Centre
  2. 2026-05: News reports: Bradford Council grants planning approval (live council page link still to confirm)

Sources

No live planning application link recorded yet. We do not upgrade a site past “proposed” without one.

Map point: longitude -1.777, latitude 53.793. Last reviewed 2026-07-15.