The Yorkshire Compute Belt

Sites

Full list of sites on the map: the power, land, and water figures behind the regional AI and cloud build-out. Each row links to more detail, including where each figure comes from.

Stated size is how large this site claims to be, in megawatts: the biggest size stated for that site if published, otherwise the grid connection applied for, otherwise the first stage only, otherwise the IT-equipment load. It is a size on paper for that scheme, not day-to-day electricity use, and not a regional total. Equal figures (two 1 GW schemes) are joint maxima: neither outranks the other. Site area is land take in acres and what kind of land it is.

Water Land use
Microsoft Skelton Grange Microsoft proposed Not disclosed Not disclosed 48 acres ex-industrial / brownfield 2026-07-15
Microsoft Eggborough Microsoft proposed Not disclosed Not disclosed Unknown ex-industrial / brownfield 2026-07-15
Drax data centre Drax proposed 100 MW · first stage only Not disclosed Unknown active industrial 2026-07-15
Elsham Tech Park Elsham Tech Park Ltd in planning 1,000 MW · biggest size stated for this site Not disclosed 435 acres farmland 2026-07-15
Humber Tech Park Humber Tech Park Ltd approved 384 MW · IT equipment only Not disclosed 188 acres farmland 2026-07-15
Deep Green Bradford Deep Green proposed 5.6 MW · biggest size stated for this site Zero claimed 0.85 acres active industrial 2026-07-15
Mountpark Ferrybridge (data-centre plot) Undisclosed (Mountpark / Affinius land) proposed Not disclosed Not disclosed 40 acres ex-industrial / brownfield 2026-07-15
Wilton International data centre (Phase 1) Sembcorp Energy UK / Digital Reef proposed 280 MW · biggest size stated for this site Not disclosed 38 acres active industrial 2026-07-15
Teesworks data centre campus Teesworks Limited / South Tees Group approved Not disclosed Not disclosed 115 acres ex-industrial / brownfield 2026-07-15
Latos Preston Farm (Stockton) Latos Data Centres proposed 9.5 MW · biggest size stated for this site Not disclosed Unknown active industrial 2026-07-15
aql Leeds data centres aql operating Not disclosed Not disclosed Unknown ex-industrial / brownfield 2026-07-26

What each site discloses

Presence of a public figure only. Not a score: five separate yes/no answers, not a grade. “Energy source” means an on-record claim about where power comes from (for example renewables or heat reuse), not a verified supply mix.

Site Stated size (MW) Water use Power usage effectiveness Energy source claim Load factor
Microsoft Skelton Grange No No No Yes No
Microsoft Eggborough No No No No No
Drax data centre Yes No No No No
Elsham Tech Park Yes No No No No
Humber Tech Park Yes No No No No
Deep Green Bradford Yes Claims zero No Yes No
Mountpark Ferrybridge (data-centre plot) No No No No No
Wilton International data centre (Phase 1) Yes No No No No
Teesworks data centre campus No No No No No
Latos Preston Farm (Stockton) Yes No No No No
aql Leeds data centres No No No No No

Load factor is how much of peak capacity a site expects to use on average. No operator on this map publishes one.