The Yorkshire Compute Belt

Sites / Teesworks data centre campus

Teesworks data centre campus

Teesworks Limited / South Tees Group · approved · Redcar and Cleveland Borough Council

Reserved-matters approval (August 2025) for a data-centre campus extending over about 462,419 m² (≈115 acres — the site extent as reported, not a floorspace figure) on the former Redcar sinter plant / Foundry land within Teesworks, pursuant to outline permission R/2020/0821/ESM. Megawatt capacity is not disclosed in the officer report reviewed so far. The scheme competed for land with BP’s H2Teesside hydrogen proposal; BP formally withdrew H2Teesside in December 2025.

Stated size

Not disclosed

No megawatt figure in materials reviewed

Operators often omit a megawatt figure. Map circles then use site area instead. Stated size is not electricity use.

Site area

115 acres

ex-industrial / brownfield Operator

What was here: Former Redcar sinter plant / Teesworks Foundry outline site (ex-steelworks)

Water

Not disclosed

No annual water figure in materials reviewed

Equivalences

No operator on this map discloses expected load factor (the share of peak power used on average), so yearly electricity figures are shown as a range, not as a known total.

Grid connection

Substation and battery stores listed in the reserved-matters description. A campus megawatt figure is not stated in the officer report reviewed; consultees noted power requirements may need fuller assessment. Planning

Claims on record

Disclosure checklist

Plain checklist, no aggregate score.

Right of reply

Right of reply: open; no response received. Email marco@prismaticlabs.ai. Subject is prefilled. Or see methodology.

Timeline

  1. 2022-03: Outline permission R/2020/0821/ESM for Foundry B2/B8/E floorspace
  2. 2025-02: Reserved matters for access road / security cabin approved (R/2024/0820/ESM)
  3. 2025-08-01: Reserved matters approved for data-centre campus R/2025/0382/ESM (appearance, landscaping, layout, access, scale)
  4. 2025-12: BP formally withdraws the H2Teesside development consent order bid, citing material changes at Teesworks; ends the land conflict with the data-centre scheme

Controversies / contested procedure

Land conflict with BP H2Teesside hydrogen DCO proposals on overlapping Teesworks land; both framed as nationally significant. Resolved December 2025 when BP formally withdrew H2Teesside

Source

Sources

Planning application R/2025/0382/ESM: live portal

Map point: longitude -1.145, latitude 54.61. Last reviewed 2026-07-15.