The Yorkshire Compute Belt

Sites / Humber Tech Park

Humber Tech Park

Humber Tech Park Ltd · approved · North Lincolnshire Council

Outline permission for up to three data-centre buildings with up to 384 MW of IT load (about 309,000 m² of floorspace) on land south of the A160, South Killingholme. Trade press reported 386 MW; the planning statement says 384 MW. Shares directors with Elsham Tech Park Ltd; Greystoke Land links reported.

Stated size

384 MW

IT equipment only Planning

Source: https://www.humbertechpark.com/_files/ugd/3dd663_993ebfa9537649b787c55d32ef55b587.pdf (Planning Statement: up to three data-centre buildings capable of 384MW of IT load)

Power for the computers alone, as written in planning materials. Still a stated size, not metered use. Stated size is not electricity use.

Site area

188 acres

farmland Planning

What was here: Greenfield / undeveloped land south of the A160

Water

Not disclosed

No annual water figure in materials reviewed

Equivalences

No operator on this map discloses expected load factor (the share of peak power used on average), so yearly electricity figures are shown as a range, not as a known total.

Grid connection

Electricity substation included in outline description. Planning

Claims on record

Disclosure checklist

Plain checklist, no aggregate score.

Right of reply

Right of reply: open; no response received. Email marco@prismaticlabs.ai. Subject is prefilled. Or see methodology.

Timeline

  1. 2024-08: North Lincolnshire Council grants outline planning permission (PA/2024/584)

Sources

Planning application PA/2024/584: live portal

Map point: longitude -0.255, latitude 53.643. Last reviewed 2026-07-15.