The Yorkshire Compute Belt

Sites / Mountpark Ferrybridge (data-centre plot)

Mountpark Ferrybridge (data-centre plot)

Undisclosed (Mountpark / Affinius land) · proposed · Wakefield Council

About 40 acres within the former Ferrybridge C coal-yard redevelopment (Mountpark Ferrybridge), reported sold or reserved for a data centre (Zone A in trade press). The live Wakefield consent linked here is the wider hybrid employment permission for the 110-acre site (decided / approved); a dedicated data-centre size in megawatts and a red-line for Zone A alone are not yet confirmed in materials reviewed. We list the plot as proposed until those are sourced.

Stated size

Not disclosed

No megawatt figure in materials reviewed

Operators often omit a megawatt figure. Map circles then use site area instead. Stated size is not electricity use.

Site area

40 acres

ex-industrial / brownfield Operator

What was here: Former Ferrybridge C power station coal stock yard (brownfield)

Water

Not disclosed

No annual water figure in materials reviewed

Equivalences

No operator on this map discloses expected load factor (the share of peak power used on average), so yearly electricity figures are shown as a range, not as a known total.

Claims on record

None recorded yet.

Disclosure checklist

Plain checklist, no aggregate score.

Right of reply

Right of reply: open; no response received. Email marco@prismaticlabs.ai. Subject is prefilled. Or see methodology.

Timeline

  1. 2024-10-04: Wakefield hybrid consent for Mountpark Ferrybridge enabling works and outline employment floorspace (22/02485/HYB) reported decided / approved
  2. 2025: Trade press: Zone A / about 40 acres taken forward or sold for a data centre within the Ferrybridge masterplan

Sources

Planning application 22/02485/HYB: live portal

Map point: longitude -1.281, latitude 53.715. Last reviewed 2026-07-15.