The pipeline

This page adds up the stated megawatts on the map and groups them by how far each scheme has got: running, being built, consented, or still only proposed. It counts what is on the public record and does not try to predict what gets built. Stated size is capacity on paper, not the electricity a site draws day to day, and plenty of these schemes will not happen.

980 MW

operating today (62 sites)

2,030 MW

under construction, consented, or proposed

2.1×

more capacity coming than is running now

Capacity by build maturity

≈3,010 MW stated across 87 sites (campus overlays and closed sites excluded).

Where it is heading

The running capacity sits in the old west (Slough) and east (Docklands) clusters; the largest proposed schemes are pushing out to the north and east M25 fringe.

West (Slough–Heathrow) 1,196 MW
East (Docklands, Thames) 1,012 MW
North fringe 752 MW
South fringe 35 MW
Inner London 14 MW

The numbers

Maturity Stated MW Share Sites
Operating 980 33% 62
Under construction 386 13% 7
Consented, not built 808 27% 13
Proposed 836 28% 5
Total (live + pipeline) 3,010 100% 87
Closed (excluded) — — 1

How to read this